What to do when furniture arrives damaged

Rory Goshima 5 min read

A receiving warehouse should photograph and inspect every item, then tell you about damage before the vendor’s deadline.

Last updated

The warehouse sends one photograph of a closed carton and marks the chair as received. The installers open it weeks later and find a crushed leg. The vendor’s claim window has closed, so the studio is left with a delayed room and a bill nobody expected.

That failure began at receiving. “Arrived” told the designer where the chair was. It said nothing about which chair was in the box or whether it could be installed.

Business of Home spoke to designers who brought receiving in-house after dealing with damaged goods, weak photographs, and late reports. Most studios will keep using a warehouse. They need a receiving agreement precise enough to catch the same problems.

Put the claim date on the purchase record

Damage terms vary across vendors and carriers. Some deadlines begin at delivery; others depend on inspection or written notice. “Report damage promptly” is useless when the team needs an exact date.

For each order, record when the claim period begins, when it ends, what proof the vendor asks for, and who will submit the claim. Give the warehouse the inspection date before the truck arrives. If the terms are vague, ask the vendor to confirm them in writing and attach the reply to the purchase record.

This is tedious administrative work. When nobody does it, the studio may miss the claim date.

Define inspection box by box

A receiver may count the cartons and call the delivery inspected. The designer may assume every carton was opened and checked. Write down what the service includes.

For a chair, inspection may mean checking the model, finish, dimensions, legs, upholstery, and hardware, then photographing the packaging and every side of the piece. A chandelier needs a component count. Two identical cartons need two separate checks.

Designer Blair Moore told Business of Home that her receiver photographed one chair from a pair. The second stayed boxed until installation, when the team discovered it was the wrong chair. The photograph proved the condition of one item. It gave the studio no evidence about the other.

Sampling works for some warehouse jobs. Individually specified pieces need individual checks.

Give each item one record

“Dining chairs received” can hide multiple cartons and one missing finish. Record each item against its purchase order and tracking details. Add the arrival date, inspection photographs, storage location, and current status.

Use statuses that tell the next person what to do: awaiting inspection, damage found, claim submitted, repair approved, replacement ordered, ready for installation. “In warehouse” describes a location. Add the inspection result so the project manager knows whether the item is usable.

For every item, record what arrived, what the receiver opened, what they found, and when the claim period ends.

Send the studio a report it can act on

A damage report needs the item number, photographs of the damage and packaging, the inspection date, and a note about missing parts. Send it to a named studio contact through the agreed channel while the item is still open.

Photographs uploaded to a portal can wait unseen. An email that says “lamp damaged” sends the designer searching through orders. The useful message is closer to this:

{Item name and purchase-order reference}. {Damage found}. Packaging and damage photographs attached. The vendor’s notice deadline is {date}. The item remains in receiving.

The studio can now check the terms, contact the vendor, and update the project schedule. Keep the item and its packaging until the vendor or carrier confirms what happens next.

Check the warehouse before installation

Choose a handful of recent deliveries and compare the portal with the physical stock. Open the photographs. Check the dates. Confirm that each carton has its own record and that damage reached the right person.

If the same gaps keep appearing, change the instructions, service level, or receiver. Installation day is too late to discover that “inspected” meant counting boxes.

Rory Goshima
Writer, Field Notes

Rory has never come across a boutique creative studio she didn't want to interview. She collects other people's business origin stories the way some people collect vinyl. She does her clearest thinking on long walks along the pier where she lives in California.